Bricks, Mortar, Cement, & Sand Calculation
- Get link
- X
- Other Apps
Bricks, Mortar, Cement, & Sand Calculation
BRICKS CALCULATION
L (T or W) (H or D)
Total brickwork wall
size = 10' x 0' - 9"x 10'
Volume of wall = 75cft
Actual brick size =
9" x 4 - ¼" x 3"
Mortar thickness = ½" L B D
Volume of one brick
with mortar = 9 - ½" x 4 - ½" x 3 - ½"
Volume of one brick
with mortar = 9 - 0" x 4 - ¾" x 3 - ½"
Nominal brick size = 0.0866 cft
Brick req for 75cft =
75/0.0866
= 866.16 nos
Add wastage 5-10% (100+5=105/100=1.05)
Total Brick req = 866.16x1.05 = 909.47
nos
MORTAR CALCULATION
Volume of Wall = 75cft
Brickwork volume
without mortar
per cft = 1/0.0664 = 15.059 no's
Brickwork volume with
mortar
per cft = 1/0.0866 = 11.549 no's
Volume of mortar
= 1- (volume of brickwork with mortar/volume of brick without mortar) x100
= 1 – (11.549 / 15.059)
x 100
= 1– 0.766 x 100
= 0.234 x 100
=23.4/100
Mortar thickness ½" = 0.23%
Constant value 1.33
Cement + sand + water
= Wet mortar
Voids (air + water) =
1/3 = 0.33 = 33%
100 cft =100 – 33 = 67 output = 67%
if we need 100%
output = 0.67 + 0.33+ 0.33 = 1.33
Mortar ratio for
9" wall = [ 1:5 to 1:6]
Mortar ratio for 4-¼"
wall = [ 1:4 to 1:5]
for 1/2" mortar
thickness = 23 mortar in total volume
Brickwork volume x
Mortar volume %
= 75 x 0.233
Wet volume = 17.481 cft
Dry volume = 1.33 x Wet
volume
= 1.33x17.481 =23.30 cft
CEMENT CALCULATION
Cement = 23.30 x 1/7 =
3.33 cft
One bag cement =
1.226cft / bag
= 3.33 / 1.226
= 2.716 bags
Add wastage 2%. = 2.716
x 1.02 = 2.77 ~ 2¾ bags
SAND
CALCULATION
For a 1:6 ratio, cement 1 part, and sand 6 part
cement
1 part = 3.33 cft
Sand = 6 x 3.33 = 19.98 cft
wastage 10%
= 19.98 x 1.1 = 21.97 cft
(100 cft = 1 unit) = 21.97/100
= 0.219 unit ~ ¼ unit